  1. Technical evaluation result for the project of Improvement & Rehabilitation of existing Indira Bye Pass road form Km 0.000 to km 10.117 on NH-10 in the State of Sikkim on Item Rate Basis. Dated : 29-12-2017
  2. Revised Technical evaluation result for the project of Consultancy Services for Authority’s Engineer for Supervision of “Four laning of Dolabari to Jamuguri section from km 17.300 of NH-37A to km 182.000 of NH-52 in the State of Assam under SARDP- NE, Phase A”. Dated : 27-12-2017
  3. Technical evaluation result for the project of Consultancy Services for preparation of DPR for development of Economic Corridors and International Connectivity Routes to improve the efficiency of freight movement in the state of Mizoram & Nagaland under Bharatmala Pariyojana (Lot-2). Dated : 27-12-2017
  4. Technical evaluation result for the project of Consultancy Services for carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of Two Laning with paved shoulder NH configuration of (i) Margherita-Changlang in the state of Assam and Arunachal Pradesh (ii) Daporijo (Upper Subansiri) to Dollungmukh (Lower Subansiri) via Dumporijo in the state of Arunachal Pradesh (iii) Tezu-Chapakhowa Via Sunpura section in the state of Arunachal Pradesh and Assam under SARDP-NE on Engineering, Procurement and Construction mode. Dated : 26-12-2017
  5. Technical evaluation result for the project of selection of Agency for providing services of Manpower placement in NHIDCL. Dated : 26-12-2017
  6. Technical Evaluation Result for the project of Short Tender for “Specialised Consultancy Services for ‘Good for Tender’ design based on detailed investigations, estimation, survey, costing, preparation of Detailed Project Report, Technical Schedules of EPC documents and Land Acquisition Survey and Pre-Construction activities for Construction of 4 nos. of bypasses at Chhiathlang, Serchhip, Hnathial and Lawngtlai on Aizawl Tuipang section of NH-54 in the state of Mizoram”. Dated : 12-12-2017
  7. Technical Evaluation Result for the project of Restoration / Reconstruction of Churachandpur to Tuivai(NH- 102B) road from km 103.10 to Km 161.48 (58.38 Km) in the state of Manipur on EPC mode 3rd Call. Dated : 07-12-2017
  8. Technical Evaluation Result for the project of Consultancy services for 1 year for supervision of “Restoration / Reconstruction of Ukhrul-Toloi-Tadubi road section from Km 0.00 to Km 115.00 covering 115 Km length on NH-102A in the state of Manipur”. Dated: 21-11-2017 
  9. Technical Evaluation Result for the project of Consultancy Services for Supervision of Renovation of 32 Office rooms in Transport Bhawan of Ministry of Shipping, New Delhi –110001. Dated: 20-11-2017 
  10. Technical Evaluation Result for the project of Consultancy Services for Authority’s Engineer For (2nd Call) For (i) Construction of (i) 154m span Steel Superstructure Bridge at Km 145.09 over River Barak and (ii) 122 m span Steel Superstructure Bridge at Km 189.80 over River Makru on Jiribam- Barak road on NH-53 in State of Manipur.(Pkg.I) (ii) Short Term Improvement & Routine Maintenance of Imphal-Jiribam Road from Km 3.00 to Km 220.00 (Length= 217 Km) of NH-53 (New NH-37) in the state of Manipur on Percentage Rate basis. (Pkg-II) (iii) Restoration/Reconstruction of Tamenglong-Khonsang Road (Km 0.00 to Km 39.50) in the State of Manipur (Pkg-III). Dated: 17-11-2017 
  11. Technical Evaluation Result for the project Construction of Mechi Bridge and Approaches on India-Nepal border linking Kakarvitta in Nepal and Panitanki in India under Engineering Procurement and Construction (EPC) Mode. Dated: 10-11-2017 
  12. Revised Technical Evaluation Result for the project of Consultancy Services for Authority’s Engineer for Supervision of “ (i) Rehabilitation and up-gradation of Tura-Mankachar road from Mirjumala junction to Mankachar-Silchar Tinali (0/0 to 1/660km) to two lane carriageway in the State of Assam (ii) Rehabilitation and up-gradation of Doimukh-Harmuti road from Harmuti Junction (0/00 km) to Khula camp (14/370 km) and Doimukh (0/000 km) to Bagh Tinali (3/100 km) two lane carriageway in the State of Assam and Arunachal Pradesh (iii) Rehabilitation and up-gradation of Wokha-Merapani Road from Wokha Junction (0/000 km) To (26/000 km) in the State of Nagaland (iv) Rehabilitationand up-gradation of Wokha-Merapani Road from (26/000 km) To (48/000 km) in the State of Nagaland (v) Rehabilitation and up-gradation of Wokha-Merapani Road from (48/000 km) To Merapani (60/585 km) in the State of Nagaland and Assam”. Dated: 09-11-2017 
  13. Technical Evaluation Result for the project of Consultancy Services for carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services of new RCC Bridge over River Gomti at Ch. 49.80 km and over River Muhuri at Ch. 93.775 km including approach roads to the Bridges on Agartala to Sabroom road section of NH-44 in the state of Tripura. Dated : 31-10-2017
  14. Technical Evaluation Result for the project of Construction of Major Bridge over Middle Strait Creek between Km. 106.590 to Km. 107.762 of NH-223 (New No.- NH-4) connecting South Andaman & Baratang Islands in the Union Territory of Andaman & Nicobar Islands on EPC Basis. Dated: 31-10-2017
  15. Technical Evaluation Result for the project of Four Laning of Jhanji to Demow Section of NH-37 from Km 491.050 to Km 535.250 (Design Km 490.800 to Km 534.800) in the state of Assam under SARDP-NE on Engineering, Procurement and Construction Mode. Dated: 31-10-2017
  16. Technical Evaluation Result for the project of Four Laning of Jorhat to Jhanji Section of NH-37 from Km 453.000 to Km 491.050 (Design Km 453.000 to Km 490.800) in the state of Assam under SARDP-NE on Engineering, Procurement and Construction Mode. Dated: 31-10-2017
  17. Technical Evaluation Result for the project of Rehabilitation of Existing Road Churachandpur- Singhat- Tuvai (NH-102 B) Between Km. 0.000 To Km. 34.5 (Net Length= 34.50 Km.) In the State Of Manipur On EPC Basis (3rd Call). Dated : 27-10-2017
  18. Technical Evaluation Result for the project of Consultancy Services for Preparation, Submission & Clearance of Land Acquisition Plan, Utility Shifting and Forest Clearance proposals for widening and upgradation of National Highways in the North Eastern Region (NER) of India. Dated : 27-10-2017
  19. Technical Evaluation Result for the project of Short term operation and maintenance from km. 403.000 to km 468.000 of NH-07 (old NH-58) in Rudraprayag-Joshimath in the State of Uttarakhand- Package-II. Dated : 24-10-2017
  20. Technical Evaluation Result for the project of Short term operation and maintenance from km. 368.000 to km 403.000 of NH-07 (old NH-58) in Rudraprayag-Joshimath in the State of Uttarakhand- Package-I. Dated : 24-10-2017
  21. Financial Bid Opening for the project of Consultancy Services for Authority Engineer for Supervision of “Construction of Four/Six laning from Km 132.375 to Km 158.058 (Total New Alignment length of 20.683 Km) of Daboka Dimapur Section (Dimapur Bypass) of NH-36 & 39 in the state of Nagaland and Dimapur Bypass (Assam Portion) from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] (length 14.325 Km) in the State of Assam under SARDP-NE on Engineering Procurement and Construction basis. Dated : 24-10-2017
  22. Technical Evaluation Result for the project of Consultancy Services for Authority’s Engineer for Supervision of “ (i) Rehabilitation and up-gradation of Tura-Mankachar road from Mirjumala junction to Mankachar-Silchar Tinali (0/0 to 1/660km) to two lane carriageway in the State of Assam (ii) Rehabilitation and up-gradation of Doimukh-Harmuti road from Harmuti Junction (0/00 km) to Khula camp (14/370 km) and Doimukh (0/000 km) to Bagh Tinali (3/100 km) two lane carriageway in the State of Assam and Arunachal Pradesh (iii) Rehabilitation and up-gradation of Wokha-Merapani Road from Wokha Junction (0/000 km) To (26/000 km) in the State of Nagaland (iv) Rehabilitationand up-gradation of Wokha-Merapani Road from (26/000 km) To (48/000 km) in the State of Nagaland (v) Rehabilitation and up-gradation of Wokha-Merapani Road from (48/000 km) To Merapani (60/585 km) in the State of Nagaland and Assam”. Dated : 24-10-2017
  23. Financial Bid Opening for the project of Consultancy Services for Authority Engineer for Supervision of “ Construction of Two-Laning of Akajan – Likabali- Bame Road on EPC basis from existing Km 71.000 to 99.000 (design Km. 65.810 to Km. 91.928) in the state of Arunachal Pradesh under SARDP-NE on Engineering Procurement & Construction (EPC) Mode.” Dated : 24-10-2017
  24. Financial Bid Opening for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from (i) design Km. 77+363 to Km. 92+363 [existing Km 88.700 to Km 104.850] (ii) design Km. 92+363 to Km. 107+363[ existing Km 104.850 to Km 122.600] (iii) design Km. 107+363 to Km. 122+353[existing Km 122.600 to Km 138.000] (iv) design Km. 122+353 to Km. 138+389 [Existing Km 138.00 to Km 158.00] in the state of Arunachal Pradesh under SARDPNE On Engineering, Procurement & Construction Mode. Dated : 24-10-2017
  25. Financial Bid Opening for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Meka-Roing-Hunli from existing Km 16 of Roing Hunli Road to Km 21.5 of Hunli-Anini Road (Total Length = 74.863 Km) to NH double lane specification in Arunachal Pradesh on Engineering Procurement and Construction (EPC) basis.” Dated : 24-10-2017
  26. Modified Technical Evaluation Score for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the UT of Andaman & Nicobar Islands. Dated : 13-10-2017
  27. Technical Evaluation Result for the project of Urgent repairs of Bridge at Bhandarkot in District Kishtwar on Batote-Kishtwar-Sinthanpass Road, NH-244 in the state of Jammu & Kashmir. Dated : 13-10-2017
  28. Modified Technical Evaluation Score for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the state of Assam. (Package 1). Dated : 13-10-2017
  29. Modified Technical Evaluation Score for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the state of Assam (Package 2). Dated : 13-10-2017
  30. Modified Technical Evaluation Score for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the state of Assam (Package 3) Dated : 13-10-2017.
  31. Technical Evaluation Result for the project of Consultancy Services for Authority’s Engineer for Supervision of “Four laning of Dolabari to Jamuguri section from km 17.300 of NH-37A to km 182.000 of NH-52 in the State of Assam under SARDP- NE, Phase A. Dated : 13-10-2017
  32. Technical Evaluation Result for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from (i) design Km. 77+363 to Km. 92+363 [existing Km 88.700 to Km 104.850] (ii) design Km. 92+363 to Km. 107+363[ existing Km 104.850 to Km 122.600] (iii) design Km. 107+363 to Km. 122+353[existing Km 122.600 to Km 138.000] (iv) design Km. 122+353 to Km. 138+389 [Existing Km 138.00 to Km 158.00] in the state of Arunachal Pradesh under SARDPNE On Engineering, Procurement & Construction Mode. Dated : 05-10-2017
  33. Technical Evaluation Result for the project of Consultancy Services for Authority Engineer for Supervision of “ Construction of Two-Laning of Akajan – Likabali- Bame Road on EPC basis from existing Km 71.000 to 99.000 (design Km. 65.810 to Km. 91.928) in the state of Arunachal Pradesh under SARDP-NE on Engineering Procurement & Construction (EPC) Mode. Dated : 05-10-2017
  34. Technical Evaluation Result for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Meka-Roing-Hunli from existing Km 16 of Roing Hunli Road to Km 21.5 of Hunli-Anini Road (Total Length = 74.863 Km) to NH double lane specification in Arunachal Pradesh on Engineering Procurement and Construction (EPC) basis. Dated : 05-10-2017
  35. Technical Evaluation Result for the project of Four Laning of Balachera to Harangajo section of NH-54(Ext) from km 275.000 to km 244.000 in the State of Assam on EPC mode. Dated: 27-09-2017
  36. Technical Evaluation Result for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the UT of Andaman & Nicobar Islands. Dated: 26-09-2017
  37. Technical Evaluation Result for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in North Eastern Region (NER) (Package 1). Dated: 26-09-2017
  38. Technical Evaluation Result for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in North Eastern Region (NER) (Package 2). Dated: 26-09-2017
  39. Technical Evaluation Result for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the state of Assam. (Package 1). Dated: 26-09-2017
  40. Technical Evaluation Result for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the state of Assam. (Package 2). Dated: 26-09-2017
  41. Technical Evaluation Result for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the state of Assam. (Package 3). Dated: 26-09-2017
  42. Technical Evaluation Result for the project of Consultancy Services for Authority Engineer for Supervision of “Construction of Four/Six laning from Km 132.375 to Km 158.058 (Total New Alignment length of 20.683 Km) of Daboka Dimapur Section (Dimapur Bypass) of NH-36 & 39 in the state of Nagaland and Dimapur Bypass (Assam Portion) from existing Km 159.400 of NH-36 to existing Km 102.500 of NH-39 and upto end point of Assam portion [Design Km 118.050 to design Km 132.375] (length 14.325 Km) in the State of Assam under SARDP-NE on Engineering Procurement and Construction basis. Dated: 25-09-2017
  43. Technical Evaluation Result for the project of Consultancy Services for Preparation of Detailed Project Report for Construction of 2-Lane Bridge for Connectivity of Port Blair – Chatham Island and Bambooflat with 400 M Navigational span in the Union Territory region of Andaman Nicobar Islands. Dated: 22-09-2017
  44. New Technical Evaluation Result for the project of Consultancy Services For Authority’s Engineer For (i) Rehabilitation and Up-gradation of Beodnabad – Ferrargunj Section of NH-223 (New NH-4) from Km 12.0 to Km 45.0 (excluding Km 21.0 to Km 28.0), to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis. (Pkg-I) (ii) Rehabilitation and up-gradation of section from Km 242.0 to 298.0 of NH-223(New NH- 4) to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis. (Pkg-II) (iii) Construction of Major Bridge over Humphrey Strait Creek between Km. 129.420 to Km. 130.600 of NH-223 (New NH-4) connecting Middle & North Andaman Islands in the Union Territory of Andaman & Nicobar Islands on EPC Basis. (Pkg.III). Dated: 22-09-2017
  45. Technical Evaluation Result for the project of Renovation of 32 Office rooms in Transport Bhawan of Ministry of Shipping, New Delhi –110001. Dated: 22-09-2017
  46. New Technical Evaluation Result for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of (i) 2 laning with paved shoulder of Churachandpur -Tuivai road section (length 162Km ) on NH-102B in the State of Manipur (ii) 2 laning with paved shoulder of Imphal-Jiribam section of NH-37 (NH-53) (length 220 Km) in the State of Manipur (iii) 2 laning with paved shoulder from Tamenglong in Manipur to Peren in Nagaland via Longdi Pabram (length-100Km) (2nd Call). Dated: 15-09-2017
  47. Technical Evaluation result for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from (i) design Km. 20+000 to Km. 32+050 [Existing Km 20.000 to Km 35.150] (ii) design Km. 32+050 to Km. 44+000 [Existing Km 35.150 to Km 50.050] (iii) design Km. 44+000 to Km. 59+363 [Existing Km 50.000 to Km 70.000] (iv) design Km. 59+363 to Km. 77+363 [Existing Km 70.00 to Km 88.700] in the state of Arunachal Pradesh under SARDPNE On Engineering, Procurement & Construction (EPC) Mode. Dated : 15-09-2017
  48. Final Technical Evaluation result for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of 2 laning of (i) Maram-Peren-Dimapur section on NH 129A (Manipur & Nagaland), (ii) Pallel- Chandel Section of NH-102C and (iii) Sangshak-Nampisha on NH 102 A (A Bharatmala Project) on Engineering, Procurement and Construction mode in the state of Manipur. (2nd Call). Dated: 13-09-2017
  49. Technical Evaluation result for the project of Construction of Road, Bridge and Slope Protection Works of Landslide at Bareti (Ex.km 100.300 to Km 101.60 of NH-34) in the State of Uttarakhand on EPC basis. Dated : 11-09-2017
  50. Technical Score for the Project Of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Two- Laning of Existing Khupa – Hayuliang – Hawai Road on EPC basis from (i) design Km. 0.000 (Khupa) to Km. 17.000 [Existing Km 95.800 of (Khupa – Hayuliang Road) to Km 8.970 (Hayuliang – Hawai Road)] (ii) design Km. 17.000 (Khupa) to Km. 34.000 [Existing Km 16.950 to Km 34.310 (Hayuliang – Hawai Road)] (iii) design Km. 34.000 to Km. 51.825 [Existing Km 26.625 to Km 45.050 (Hayuliang – Hawai Road)] (iv) Two-Laning of Hayuliang– Hawai bypass Road on EPC basis from design Km. 51.825 to Km. 63.131 [Existing Km 45.050 of Hayuliang – Hawai road to Hawai Town]” in the state of Arunachal Pradesh Under SARDP-NE. Dated : 07-09-2017
  51. Financial Evaluation result for the project of Selection of NGO to assist in resettlement plan implementation for IMPHAL – MOREH road in the state of Manipur. Dated : 05-09-2017
  52. New Technical Evaluation result for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of 2 laning of (i) Maram-Peren-Dimapur section on NH 129A (Manipur & Nagaland), (ii) Pallel- Chandel Section of NH-102C and (iii) Sangshak-Nampisha on NH 102 A (A Bharatmala Project) on Engineering, Procurement and Construction mode in the state of Manipur (2nd Call). Dated : 29-08-2017
  53. Technical Evaluation result for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of (i) 2 laning with paved shoulder of Churachandpur -Tuivai road section (length 162Km ) on NH-102B in the State of Manipur (ii) 2 laning with paved shoulder of Imphal-Jiribam section of NH-37 (NH-53) (length 220 Km) in the State of Manipur (iii) 2 laning with paved shoulder from Tamenglong in Manipur to Peren in Nagaland via Longdi Pabram (length-100Km) (2nd Call). Dated : 25-08-2017
  54. Technical Evaluation result for the project of Rehabilitation of existing Churachandpur-Singhat- Tuvai road on NH-102 B between km. 103.10 to Km. 161.48 (length 58.38 km.) in the state of Manipur on EPC basis (2nd call). Dated : 25-08-2017
  55. Technical Evaluation result for the project of CONSULTANCY SERVICES FOR AUTHORITY’S ENGINEER FOR (i) Construction of (i) 154m span Steel Superstructure Bridge at Km 145.09 over River Barak and (ii) 122 m span Steel Superstructure Bridge at Km 189.80 over River Makru on Jiribam- Barak road on NH-53 in State of Manipur.(Pkg.I) (ii) Short Term Improvement & Routine Maintenance of Imphal-Jiribam Road from Km 3.00 to Km 220.00 (Length= 217 Km) of NH-53 (New NH-37) in the state of Manipur on Percentage Rate basis. (Pkg-II) (iii) Restoration/Reconstruction of Tamenglong-Khonsang Road (Km 0.00 to Km 39.50) in the State of Manipur. (Pkg-III) Dated : 18-08-2017
  56. Technical Evaluation result for the project of CONSULTANCY SERVICES FOR AUTHORITY’S ENGINEER FOR (i) Rehabilitation and Up-gradation of Beodnabad – Ferrargunj Section of NH-223 (New NH-4) from Km 12.0 to Km 45.0 (excluding Km 21.0 to Km 28.0), to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis. (Pkg-I) (ii) Rehabilitation and up-gradation of section from Km 242.0 to 298.0 of NH-223(New NH- 4) to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis. (Pkg-II) (iii) Construction of Major Bridge over Humphrey Strait Creek between Km. 129.420 to Km. 130.600 of NH-223 (New NH-4) connecting Middle & North Andaman Islands in the Union Territory of Andaman & Nicobar Islands on EPC Basis. (Pkg.III) Dated : 18-08-2017
  57. Technical Evaluation result for the project of Selection of NGO to assist in resettlement plan implementation for IMPHAL – MOREH road in the state of Manipur. Dated: 18-08-2017
  58. Technical Evaluation Score for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from (i) design Km. 20+000 to Km. 32+050 [Existing Km 20.000 to Km 35.150] (ii) design Km. 32+050 to Km. 44+000 [Existing Km 35.150 to Km 50.050] (iii) design Km. 44+000 to Km. 59+363 [Existing Km 50.000 to Km 70.000] (iv) design Km. 59+363 to Km. 77+363 [Existing Km 70.00 to Km 88.700] in the state of Arunachal Pradesh under SARDPNE On Engineering, Procurement & Construction (EPC) Mode. Dated : 17-08-2017
  59. Revised Technical Evaluation result for the project of Consultancy Services for Authority’s Engineer for Supervision of “(i) Construction of Extra-dosed RCC Bridge including viaduct and approaches over river Feni at Sabroom on Indo-Bangladesh Border on NH-8 in the state of Tripura on EPC mode, (ii) Two laning with paved shoulder of NH-53 from Silchar to Badarpur section from km 6.25 to km 10.40 (Total Length 4.77 km) in the state of Assam on EPC basis under SARDP-NE, (iii) Improvement and Strengthening of Road section from Chand Khera to Kurti Bridge on NH-208A (Length- 17.950 km) in the state of Assam near Assam- Tripura Border”. Dated : 16-08-2017
  60. Technical Evaluation result for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of 2 laning of (i) Maram-Peren-Dimapur section on NH 129A (Manipur & Nagaland), (ii) Pallel- Chandel Section of NH-102C and (iii) Sangshak-Nampisha on NH 102 A (A Bharatmala Project) on Engineering, Procurement and Construction mode in the state of Manipur (2nd Call). Dated : 04-08-2017
  61. Technical Evaluation result for the project of Consultancy Services for Authority’s Engineer for: i) Rehabilitation and up-gradation of Beodnabad-Ferrargunj Section of NH-223 (New NH-4) from Km 12.0 to Km 45.0 (excluding Km 21.0 to Km 28.0), to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis, ii) Rehabilitation and up-gradation of section from Km 242.0 to 298.0 of NH-223 (New NH- 4) to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis, iii) Construction of Major Bridge over Humphrey Strait Creek between Km.129.420 to Km. 130.600 of NH-223 (New NH-4) connecting Middle & North Andaman Islands in the Union Territory of Andaman & Nicobar Islands on EPC Basis. Dated : 03-08-2017
  62. Technical Score for the Project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Two- Laning of Existing Khupa – Hayuliang – Hawai Road on EPC basis from (i) design Km. 0.000 (Khupa) to Km. 17.000 [Existing Km 95.800 of (Khupa – Hayuliang Road) to Km 8.970 (Hayuliang – Hawai Road)] (ii) design Km. 17.000 (Khupa) to Km. 34.000 [Existing Km 16.950 to Km 34.310 (Hayuliang – Hawai Road)] (iii) design Km. 34.000 to Km. 51.825 [Existing Km 26.625 to Km 45.050 (Hayuliang – Hawai Road)] (iv) Two-Laning of Hayuliang– Hawai bypass Road on EPC basis from design Km. 51.825 to Km. 63.131 [Existing Km 45.050 of Hayuliang – Hawai road to Hawai Town]” in the state of Arunachal Pradesh Under SARDP-NE. Dated : 25-07-2017
  63. Tender Evaluation result of project Construction, Operation and Maintenance of 2-lane bi-directional zojila tunnel with parallel escape (egress) tunnel including approaches on srinagar-leh section connecting nh-1 at km 95.00 and at km 118.00 in the state of Jammu & Kashmir on EPC Mode. Dated : 21-07-2017
  64. Technical Score for the Project of Two/ Four laning of Imphal-Moreh Section of NH-39 from Km 330.00 to Km 395.680 in the State of Manipur” – Hiring of NGO. Dated : 19-07-2017
  65. Technical Evaluation Result for the Project of Routine Maintenance of Chidiya Tapu to Middle Strait from Km 0.00 to Km 107.00 (Km 0-12, 21-28 & 45-107) of NH-4 (old NH- 223) (Maintenance Package-I) in the Union Territory of Andaman and Nicobar Island. Dated : 18-07-2017
  66. Technical Evaluation Result for the Project of Routine Maintenance of Middle Strait to Rangat (Middle Andamans) from Km 107.00 to Km 220.00 (Length=113 Km) of NH-4 (old NH-223) (Maintenance Package-II) in the Union Territory of Andaman & Nicobar Island. Dated : 18-07-2017
  67. Technical Evaluation Result for the Project of Consultancy Services for supervision of (i) two laning with paved shoulder of NH-53 from Silchar to Badarpur (ii) Construction of Extra-dosed RCC bridge including viaduct and approaches over river feni (iii) Improvement and strengthening of road section from Chand Khera to Kurti bridge. Dated : 18-07-2017
  68. Financial Bid Opening Letter for the Project of Routine Maintenance of Rangat to Diglipur (North Andamans) from Km 220.00 to Km 330.70 (Length=110.7 Km) of NH-4 (old NH-223) (Maintenance Package-III) in the Union Territory of Andaman & Nicobar Island.
  69. Technical Evaluation Result for the Project of Protection works at Nalupani landslide (Ex. km. 123+080 to km.123+480, km 123+665 to km 123+740 and km 123+770 to km 123+970 sections of NH-34 in the State of Uttarakhand. on EPC Mode
  70. Technical Evaluation Result for the Project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of new National Highways in the state of Assam.(Package 2)
  71. New Technical Evaluation Score for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of (i) 2 laning with paved shoulder of Namchi-Ravangla-Tashiding-Yusksum-Geyzing road section (length-122Km) in the State of Sikkim (ii) 2 laning with paved shoulder of Geyzing-Dentam-Uttarey-Chiwabhanjang road section (length-55 Km) in the State of Sikkim (iii) 2 laning with paved shoulder of Ravong-Phamtum-Dzongu-Upper Dzongu-Chungthang road section (length-150 Km) in the State of Sikkim.”
  72. Technical Evaluation Score for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Meka-Roing-Hunli from existing Km 16 of Roing Hunli Road to Km 21.5 of Hunli-Anini Road (Total Length = 74.863 Km) to NH double lane specification in Arunachal Pradesh on Engineering Procurement and Construction (EPC) basis.
  73. Technical Evaluation Score for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of (i) 2 laning with paved shoulder of Namchi-Ravangla-Tashiding-Yusksum-Geyzing road section (length-122Km) in the State of Sikkim (ii) 2 laning with paved shoulder of Geyzing-Dentam-Uttarey-Chiwabhanjang road section (length-55 Km) in the State of Sikkim (iii) 2 laning with paved shoulder of Ravong-Phamtum-Dzongu-Upper Dzongu-Chungthang road section (length-150 Km) in the State of Sikkim.”
  74. Technical Evaluation Result for the project of Consultancy Service for Authority’S Engineer for (i) Construction of 1000m length Viaduct at Rangpo between km 51.100 to km 53.900 on Sevoke –Gangtok Road NH-10 (Old NH-31A) in the State of West Bengal/Sikkim. (ii) Construction of up-gradation of existing road to 2-lane with paved shoulder including geometric improvement from km. 0.000 to km. 26.706 in Rhenok-Rorathang-Pakong of NH-717A on EPC basis under SARDP-NE Phase ‘A’ in the State of Sikkim. (iii) Construction/up-gradation of existing road to 2-lane with paved shoulders including geometric improvement of NH-510 from km. 0.000 to km. 32.500 (Singtam-Tarku-Rabongla-Legship-Gyalshing) on EPC basis under SARDP-NE Phase ‘A’ in the State of Sikkim.
  75. Technical Evaluation Result for the project of Consultancy Services for Additional Topographical, Geological/ Geotechnical Survey and data collection from Km.85.00 to 95.00, 101.00 to 145.00 to 2- Lane with paved shoulders of Tura – Dalu of NH-51 in the State of Meghalaya.
  76. Latest Technical Evaluation Score for the project of Consultancy Service for Authority’S Engineer for (i) Construction of 1000m length Viaduct at Rangpo between km 51.100 to km 53.900 on Sevoke –Gangtok Road NH-10 (Old NH-31A) in the State of West Bengal/Sikkim. (ii) Construction of up-gradation of existing road to 2-lane with paved shoulder including geometric improvement from km. 0.000 to km. 26.706 in Rhenok-Rorathang-Pakong of NH-717A on EPC basis under SARDP-NE Phase ‘A’ in the State of Sikkim. (iii) Construction/up-gradation of existing road to 2-lane with paved shoulders including geometric improvement of NH-510 from km. 0.000 to km. 32.500 (Singtam-Tarku-Rabongla-Legship-Gyalshing) on EPC basis under SARDP-NE Phase ‘A’ in the State of Sikkim.
  77. Technical Evaluation Result for the project of Consultancy Services for Topographical, Traffic, Geological / Geotechnical Survey and Data collection for widening and upgradation of National Highways in the North East Region (NER) of India.
  78. Technical Evaluation Score for the project of Consultancy Services for Authority’s Engineer for Supervision of “Construction of Two- Laning of Existing Khupa – Hayuliang – Hawai Road on EPC basis from (i) design Km. 0.000 (Khupa) to Km. 17.000 [Existing Km 95.800 of (Khupa – Hayuliang Road) to Km 8.970 (Hayuliang – Hawai Road)] (ii) design Km. 17.000 (Khupa) to Km. 34.000 [Existing Km 16.950 to Km 34.310 (Hayuliang – Hawai Road)] (iii) design Km. 34.000 to Km. 51.825 [Existing Km 26.625 to Km 45.050 (Hayuliang – Hawai Road)] (iv) Two-Laning of Hayuliang– Hawai bypass Road on EPC basis from design Km. 51.825 to Km. 63.131 [Existing Km 45.050 of Hayuliang – Hawai road to Hawai Town]” in the state of Arunachal Pradesh Under SARDP-NE.
  79. Latest Technical Evaluation Score for the project of Consultancy Services for carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of Two Laning with paved shoulder NH configuration from Simaluguri-Bihubar on NH-702C in the State of Assam to Mon on NH 702 in the state of Nagaland on Engineering, Procurement and Construction mode.
  80. Financial Evaluation Result for the project of Four Laning of Dolabari to Jamuguri section from km 17.300 of NH-37A to km 182.000 of NH-52 in the State of Assam under SARDP- NE, Phase A on EPC mode.
  81. Financial Evaluation Result for the project of Rehabilitation and up-gradation of Wokha Merapani Road from Wokha Junction (0/000 km) to (26/000 km) in the State of Nagaland” on Engineering, Procurement & Construction (EPC) Mode.
  82. Financial Evaluation Result for the project of Rehabilitation and up-gradation of Wokha-Merapani Road from (26/000 km) to (48/000 km) in the State of Nagaland” on Engineering, Procurement & Construction (EPC) Mode.
  83. Financial Evaluation Result for the project of Rehabilitation and up-gradation of Wokha-Merapani Road from (48/000 km) to Merapani (60/585 km) in the State of Nagaland and Assam” on Engineering, Procurement & Construction (EPC) Mode.
  84. Technical Evaluation Score for the project of Consultancy Service for Authority’S Engineer for (i) Construction of 1000m length Viaduct at Rangpo between km 51.100 to km 53.900 on Sevoke –Gangtok Road NH-10 (Old NH-31A) in the State of West Bengal/Sikkim. (ii) Construction of up-gradation of existing road to 2-lane with paved shoulder including geometric improvement from km. 0.000 to km. 26.706 in Rhenok-Rorathang-Pakong of NH-717A on EPC basis under SARDP-NE Phase ‘A’ in the State of Sikkim. (iii) Construction/up-gradation of existing road to 2-lane with paved shoulders including geometric improvement of NH-510 from km. 0.000 to km. 32.500 (Singtam-Tarku-Rabongla-Legship-Gyalshing) on EPC basis under SARDP-NE Phase ‘A’ in the State of Sikkim.
  85. Technical Evaluation Score for the project of Consultancy Services for carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of Two Laning with paved shoulder NH configuration from Simaluguri-Bihubar on NH-702C in the State of Assam to Mon on NH 702 in the state of Nagaland on Engineering, Procurement and Construction mode.
  86. Technical Evaluation Result for the project of Rehabilitation and up-gradation of Wokha-Merapani Road from (48/000 km) to Merapani (60/585 km) in the State of Nagaland and Assam” on Engineering, Procurement & Construction (EPC) Mode.
  87. Technical Evaluation Result for the project of Rehabilitation and up-gradation of Wokha-Merapani Road from (26/000 km) to (48/000 km) in the State of Nagaland” on Engineering, Procurement & Construction (EPC) Mode.
  88. Technical Evaluation Result for the project of Rehabilitation and up-gradation of Wokha Merapani Road from Wokha Junction (0/000 km) to (26/000 km) in the State of Nagaland” on Engineering, Procurement & Construction (EPC) Mode.
  89. Technical Evaluation Result for the project of Rehabilitation and up-gradation of section from Km 242.0 to 298.0 of NH-223 (New NH- 4) to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis. (Package-II).
  90. Technical Evaluation Result for the project of Two-Laning of Akajan – Likabali – Bame Road on EPC basis from existing Km 71.000 to Km 99.000(design Km. 65.810 to Km. 91.928) in the state of Arunachal Pradesh under SARDP-NE On Engineering, Procurement & Construction (EPC) Mode.
  91. Technical Evaluation Score for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of (i) 2 laning with paved shoulder of Churachandpur -Tuivai road section (length- 162Km) on NH-102B in the State of Manipur (ii) 2 laning with paved shoulder of Imphal-Jiribam section of NH-37 (NH-53 (length- 220 Km) in the State of Manipur (iii) 2 laning with paved shoulder from Tamenglong in Manipur to Peren in Nagaland via Longdi Pabram (length-100Km)
  92. Technical Evaluation Result for the project of Four laning of Dolabari to Jamuguri section from km 17.300 of NH-37A to km 182.000 of NH-52 in the State of Assam under SARDP- NE, Phase A on EPC mode.
  93. Technical Evaluation Score for the project of Consultancy Services for Carrying out Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services in respect of Two Laning with paved shoulder NH configuration of Demwe-Brahmkund Section from Km. 0.00 to Km. 19.22 and Arrowa-Khupa-Hayuliang section from Km. 44.02 to Km 80.97, total length for both is 56.17 Km of Demwe-Hawai Road under SARDP-NE on Engineering, Procurement and Construction mode in the state of Arunachal Pradesh. (Retender).
  94. Technical Evaluation Result for the project of Rehabilitation of existing churachandpur- singhat – Tuivai road on NH- 102B between Km 0.000 to Km 34.5 (Length 34.50 Km) in the state of Manipur on EPC Basis (2nd call)
  95. Technical Evaluation Result for the project of Restoration/Reconstruction of Ukhrul-Toloi-Tadubi road section from km 70.00 to Km 90.00 covering 20 Km length on NH-102A in the state of Manipur.
  96. Technical Evaluation Result for the project of Restoration/ Reconstruction of Ukhrul-Toloi-Tadubi road section from Km 90.00 to Km 115.00 covering 25 Km length on NH-102A in the state of Manipur.
  97. Technical Evaluation Result for the project of Construction of Extra-dosed/ Cable Stayed RCC Bridge including viaduct and approaches over river Feni at Sabroom on Indo-Bangladesh Border on NH-8 in the state of Tripura on EPC mode.
  98. Technical Evaluation Result for the project of Construction of Four/Six laning from Km 132.375 to Km 158.058 (Total New Alignment length of 20.683 Km) of Daboka- Dimapur Section (Dimapur Bypass) of NH-36 & 39 under SARDP-NE in the state of Nagaland on Engineering Procurement and Construction basis.
  99. Financial Bid Opening Letter for the project of Short Term Improvement & Routine Maintenance of Km 51.00 to Km 93.00 of NH-10 in the State of Sikkim (Including Indra and Northern Bypass) on Percentage Rate basis.
  100. Technical Evaluation Score for the project of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from design Km. 20+000 to Km. 32+050 [Existing Km 20.000 to Km 35.150] in the state of Arunachal Pradesh under SARDP-NE” on EPC Mode
  101. Technical Evaluation Score for the project of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from design Km. 32+050 to Km. 44+000 [Existing Km 35.150 to Km 50.050] in the state of Arunachal Pradesh under SARDP-NE On Engineering, Procurement & Construction (EPC) Mode
  102. Technical Evaluation Score for the project of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from design Km. 44+000 to Km. 59+363 [Existing Km 50.000 to Km 70.000] in the state of Arunachal Pradesh under SARDP-NE On Engineering, Procurement & Construction (EPC) Mode.
  103. Technical Evaluation Score for the project of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from existing Km 70.000 to Km 88.700 (design Km. 59+363 to Km. 77+363) in the state of Arunachal Pradesh under SARDP-NE On Engineering, Procurement & Construction (EPC) Mode.
  104. Technical Evaluation Score for the project of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from existing Km 88.700 to Km 104.850 (design Km. 77+363 to Km. 92+363) in the state of Arunachal Pradesh under SARDP-NE On Engineering, Procurement & Construction (EPC) Mode.
  105. Technical Evaluation Score for the project of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from existing Km 104.850 to Km 122.600 (design Km. 92+363 to Km. 107+363) in the state of Arunachal Pradesh under SARDP-NE On Engineering, Procurement & Construction (EPC) Mode
  106. Technical Evaluation Score for the project of Two-Laning of Joram – Koloriang Road (NH-713) on EPC basis from existing Km 122.600 to Km 138.000 (design Km. 107+363 to Km. 122+353) in the state of Arunachal Pradesh under SARDP-NE On Engineering, Procurement & Construction (EPC) Mode.
  107. Technical Evaluation Score for the project of Construction of two-Lane with paved shoulders of Joram-Koloriang Raod (NH-713) on EPC basis from existing Km 138.00 to Km 158.00 [ Design Km. 122.353 to Km. 138.389] (Design Length – 16.036 KM) int he state of Arunachal Pradesh.
  108. Technical Evaluation Score for the project of Consultancy Services for Authority’s Engineer for Supervision of Construction of Four/Six laning from Km 132.375 to Km 158.058 (Total New Alignment length of 20.683 Km) of Daboka Dimapur Section (Dimapur Bypass) of NH-36 & 39 under SARDP-NE in the state of Nagaland on Engineering Procurement and Construction basis.
  109. Technical Evaluation Result for the project of Construction of 2-lane with paved shoulder including geometric improvement from Km 0.00 to Km 16.000 of stretch Singtam – Tarku of NH-510 on EPC basis under SARDP –NE Phase ‘A’ in the state of Sikkim. On Engineering, Procurement & Construction Mode.
  110. Technical Evaluation Result for the project of Construction of 2-lane with paved shoulder including Geometric improvement from Km 16.000 to Km 32.500 of stretch Tarku – Rabangla of NH-510 on EPC basis under SARDP –NE Phase ‘A’ in the State of Sikkim On Engineering, Procurement & Construction Mode.
  111. Final Technical Evaluation Result for the project of Rehabilitation and up-gradation of Doimukh-Harmuti road from Harmuti Junction (0/00 km) to Khula camp (14/370 km) and Doimukh (0/000 km) to Bagh Tinali (3/100 km) two lane carriageway in the State of Assam and Arunachal Pradesh.
  112. Technical Evaluation Result for the project of Rehabilitation and up-gradation of NH-223 from Km 12.0 to 45.0 (Beodnabad -Ferrargunj Section) excluding section between Km 21.0 to Km 28.0,to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis.
  113. Technical Evaluation Result for the project of Construction of Meka-Roing- Hunli from existing km 16 of Roing Hunli Road to km 21.5 of Hunli-Anini Road (total length=74.863 km) to NH double lane specification in Arunachal Pradesh on Engineering Procurement and Construction (EPC) basis.
  114. Technical Evaluation Result for the project of Two-Laning of Existing Khupa – Hayuliang – Hawai Road on EPC basis from design Km. 0.000 (Khupa) to Km. 17.000 [Existing Km 95.800 of (Khupa – Hayuliang Road) to Km 8.970 (Hayuliang – Hawai Road)] in the state of Arunachal Pradesh Under SARDP-NE, Project Highway.
  115. Technical Evaluation Result for the project of Two-Laning of Existing Hayuliang – Hawai Road on EPC basis from design Km. 17.000 (Khupa) to Km. 34.000 [Existing Km 16.950 to Km 34.310 (Hayuliang – Hawai Road)] in the state of Arunachal Pradesh under SARDP-NE, Project Highway.
  116. Technical Evaluation Result for the project of Two-Laning of Existing Hayuliang – Hawai Road on EPC basis from Design Km. 34.000 to Km. 51.825 [Existing Km 26.625 to Km 45.050 (Hayuliang – Hawai Road)] in the state of Arunachal Pradesh Under SARDP-NE, Project Highway.
  117. Technical Evaluation Result for the project of Two-Laning of Hayuliang– Hawai bypass Road on EPC basis from design Km. 51.825 to Km. 63.131 Existing Km 45.050 of Hayuliang – Hawai road to Hawai Town in the state of Arunachal Pradesh Under SARDP-NE.
  118. Technical Evaluation Result for the project of Rehabilitation and up-gradation of Tura-Mankachar road from Mirjumala junction to Mankachar-Silchar Tinali (0/0 to 1/660km) to two lane carriageway in the State of Assam On Engineering, Procurement & Construction (EPC) Mode.
  119. Technical Evaluation Result for the project of Construction and upgradation of existing road to 2-lane with paved shoulder including geometric improvement from Km. 0.00 0to Km. 26.706 in Rhenok-Rorathang-Pakyong of NH-717A on EPC basis under SARDP-NE Phase A in the State of Sikkim (Package –I : Rhenok to Pakyong – 26.706 Kms) On Engineering, Procurement & Construction (EPC) Mode.
  120. Technical Evaluation Result for the project of Short Term Improvement & Routine Maintenance of Imphal-Jiribam Road from Km 145.00 to Km 220.00 (Length=75 Km) of NH-53 (New NH-37) (Package-III) in the state of Manipur.
  121. Technical Evaluation Result for the project of Short Term Improvement & Routine Maintenance of Imphal-Jiribam Road from Km 75.00 to Km 145.00 (Length=70 Km) of NH-53 (New NH-37) (Package-II) in the state of Manipur.
  122. Technical Evaluation Result for the project of Short Term Improvement and Routine maintenance of Imphal- Jiribam Road from Km 3.00 to Km 75.00 (Length 72 km ) of NH-53 (New NH-37) (Package-I) in the state of Manipur
  123. Technical Evaluation Result for the project of Rehabilitation and up-gradation of NH-223 from Km 12.0 to 45.0 (Beodnabad -Ferrargunj Section) excluding section between Km 21.0 to Km 28.0,to 2-Lane with hard shoulder in the Union Territory of Andaman & Nicobar Islands on EPC Basis.
  124. Technical Evaluation Result for the project of Restoration/Reconstruction of Churachandpur to Tuivai(NH- 102B) road from km 103.10 to Km 161.48 (58.38 Km) in the state of Manipur on EPC mode.
  125. Technical Evaluation Result for the project of Construction of Major Bridge over Humphrey Strait Creek between Km. 129.420 to Km. 130.600 of NH-223 (New No. NH-4) connecting Middle & North Andaman Islands in the Union Territory of Andaman & Nicobar Islands on EPC Mode.
  126. Technical Evaluation Result for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of selected road stretch/corridor to Twolane with paved shoulders NH configuration under BHARATMALA Project and National Highways connectivity to Backward areas/Religious/Tourist places of the country.
  127. Technical Evaluation Score for project of Consultancy Services for Authority’s Engineer for Project of (i) 154 m span Steel Superstructure Bridge at Km 145.09 over River Barak and (ii) 122 m span Steel Superstructure Bridge at Km 189.80 over River Makru on Jiribam-Barak road on NH-53 in Manipur State.
  128. Technical Evaluation Result for the project of Rehabilitation and up-gradation of Doimukh-Harmuti road from Harmuti Junction (0/00 km) to Khula camp (14/370 km) and Doimukh (0/000 km) to Bagh Tinali (3/100 km) two lane carriageway in the State of Assam and Arunachal Pradesh.
  129. Final Technical Evaluation Score for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for upgradation of selected stretches/ corridors to 2-lane with paved shoulder of NH configuration under SARDP-NE project in the State of Meghalaya.
  130. Technical Evaluation Score for the project of Consultancy Services for Preparation of Detailed Project Report for Construction of 2-Lane Bridge for Connectivity of Chatham Island and Bambooflat in the Union Territory region of Andaman Nicobar Islands.
  131. Technical Evaluation Score for the project of Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for up gradation of selected road stretch/corridor to Twolane with paved shoulders NH configuration under BHARATMALA Project and National Highways connectivity to Backward areas/Religious/Tourist places of the country.
  132. Technical Evaluation Result for the Project of Four Laning of NH-37 from Rangagara to Kaliabor Tiniali (Ch 297.000 to Ch 315.315) in Nagaon District in the State of Assam Under SARDP-NE, Phase A (the “Project”) on Engineering, Procurement & Construction (EPC) Mode.
  133. Technical Score for Consultancy Services for Authority’s Engineer for Supervision of Rehabilitation of Churachandpur – Tuivai Road Section (length-161.48 Km) on NH-102B in the state of Manipur on EPC basis.
  134. Modified Technical Evaluation Score for Consultancy Services for Feasibility Study, Preparation of Detailed Project Report and providing pre-construction services for upgradation of selected stretches/ corridors to 2-lane with paved shoulder configuration in the State of Meghalaya.